Client: Brisbane State High School | Location: South Brisbane
Brisbane State High School (BSHS), a renowned co-educational state secondary school located in South Brisbane, sought modern and functional upgrades to their administration and teaching facilities. Over a series of building and refurbishment projects, CMBM upgraded BSHS’s facilities and helped the school continue to provide a leading educational space for students and teachers.
Read on to find out how we did it.
Feature image supplied by Angus Martin
CMBM were engaged to complete several construction projects over a 12-month period at Brisbane State High School, including innovative new office configurations, a storage facility, HVAC upgrades, and a building extension.
CMBM delivered functional and contemporary building upgrades for the client, providing the school’s students and administration staff with modern spaces to learn and work in. All projects were delivered during the school holidays to avoid interference with school operations.
PAC Storage Facility
CMBM constructed a storage room in the Performing Arts Centre (PAC) to provide a dedicated space to store equipment. Located on the second floor of the building, additional precautions were required to ensure construction was carried out safely and to schedule.
Works involved:
The result was a durable and complementary addition to the Performing Arts Centre that provided much needed storage space for the PAC team.
Pictured: The space before and after the construction of the PAC storage facility.
H Block Upgrades & HVAC Installation
CMBM upgraded the lobby area and installed a HVAC system to Brisbane State High School’s heritage-listed H Block. Prior to installing the new split system air conditioning unit, conduits were installed throughout the building.
As one of the oldest school buildings in Queensland, the project required careful planning and construction in order to adhere to heritage-listing requirements.
Works involved:
Pictured: HVAC conduits were installed in the heritage-listed H Block in preparation for split system air conditioning.
D Block Extension
CMBM facilitated the extension of D Block by constructing three new offices along the back wall of the building, and demolishing the wall between the classroom and existing office to extend the learning space. A final builders’ clean was carried out to prepare for the handover of the new space.
This project was completed within two weeks to ensure there was no construction during the school term.
Works included:
Pictured: CMBM constructed three new offices as part of the D Block extension for Brisbane State High School.
B Block Reconfiguration
CMBM managed the reconfiguration of B Block during the September school holidays, creating a new open plan area by moving the server room to a newly constructed space and opening up the existing server room right up to the corridor.
Works included:
Pictured: The existing server room that was relocated, and the server room wall that was demolished to allow for an open plan area near the corridor.
Completion
CMBM provided modern and functional upgrades to create better educational outcomes for Brisbane State High School. With the addition of new storage spaces and refurbishments of existing facilities, BSHS can now execute their syllabus and administrative duties more freely, effectively, and comfortably.